Groundwater Recirculation Wells

ER-199602

Objectives of the Demonstration

Groundwater circulating wells (GCWs), alternatively known as in-well vapor-stripping, are an in-situ remediation technology that integrates the principles of groundwater recirculation with air stripping of volatile organic compounds. The objective of this effort was to complete a survey of GCW technology based on demonstrations at a number of federal and public sites documenting the successes and shortcomings of system performance. An additional objective was to document and develop guidelines for the use of the technology and make recommendations for additional data requirements to either support or argue against the use of this technology for particular contaminant and hydrogeologic applications.

Back to Top

Demonstration Results

Demonstration results showed various degrees of operational success. Although contamination reduction was achieved, deficiencies in hydraulic performance were experienced, resulting in lower than anticipated groundwater capture and throughput through the treatment wells. To ensure the appropriate use of GCW technology by the Department of Defense (DoD), a Groundwater Circulating Well Technology Assessment document was produced. This document provides: (1) an overview of the GCW technology; (2) a description of the GCW products offered by different vendors; (3) nine detailed DoD case histories; (4) a discussion of GCW limitations; and (5) an overall assessment of the technology.

Back to Top

Implementation Issues

GCW is an innovative in-situ technology that could reduce the time and cost required to achieve remediation goals compared to conventional technologies such as soil vapor extraction and pump-and-treat (P&T) systems. However, meaningful performance comparisons with conventional P&T systems have not been made, although capital costs up to $180k and annual operating and maintenance (O&M) costs of $42-72k were documented.

Even though GCW systems have been installed at more than 100 sites in the U.S. and Europe, the technology at its current level of maturity is more suited to sites with relatively uniform hydrogeology, and for contaminant degradation in source areas rather than for plume containment. Detailed hydrogeological characterization, particularly to determine vertical hydraulic conductivity through the aquifer would be necessary for more complex sites (with associated, additional cost). However, implementation of GCW technology at DoD remediation sites, if appropriate, could potentially reduce both capital and annual operating costs compared to conventional P&T technology by avoiding high energy costs and ex-situ treatment of secondary waste streams. (Project Completed - 1999)

Back to Top

Project Documents

Points of Contact

Program Manager

Environmental Restoration

SERDP and ESTCP

Project Documents

Document Types

  • Fact Sheet - Brief project summary with links to related documents and points of contact.
  • Final Report - Comprehensive report for every completed SERDP and ESTCP project that contains all technical results.
  • Cost & Performance Report - Overview of ESTCP demonstration activities, results, and conclusions, standardized to facilitate implementation decisions.
  • Technical Report - Additional interim reports, laboratory reports, demonstration reports, and technology survey reports.
  • Guidance - Instructional information on technical topics such as protocols and user’s guides.
  • Workshop Report - Summary of workshop discussion and findings.
  • Multimedia - On demand videos, animations, and webcasts highlighting featured initiatives or technologies.
  • Model/Software - Computer programs and applications available for download.
  • Database - Digitally organized collection of data available to search and access.